Thursday, August 6, 2009

Thursday updates


So tomorrow was suppose to be our 2nd change at
the final occupancy walk through. Yet again there were issues.
This time a structural engineer has to look at calcs on
bridge railing for we changed design to use wood
instead of metal. Of course the guy was
have used is out of town, so we are in
scramble mode. New tentative date
is Tuesday. We have 3
inspections tomorrow for stormwater items.
We are moving our stuff in Saturday for our
apartment is rented as of Monday morning

We planted some Natives in the side planters

in hopes of passing the inspection on Friday.

Side view of bridge- hoping to be built
and capped tomorrow. Asmir
and Enrique have been a huge help to us.

We have railings now on the stairs





Upper driveway is finished.
Not driveable yet but walkable.
Rockwall inspection passed today