Guess one of our inspections didn't go well today,
there was piping issues with one of the planters.
Will be working on that issue and
then calling for reinspection of the planter pipes
and then the planters. Still can't install planter plants till all
planters are completely inspected.
The other issue from today is that one of the subs hit a
wire in the Master Bedroom when they
were installing trim. This will be a action
item for tomorrow.
Each day brings some new, exciting issue. Counter tops instlaled in Guest room on built ins


Frosted and non frosted glass installed on roof deck. Other glass
purchased but not yet installed on bridge. Bridge clad work still
needs to be worked on but first floors need to be installed

Rugs on stairs covered but carpeted. Too many people
walking around the house/saw dust
and whatever else makes covering them a necessity.





Everything covered for more painting in Kitchen




Prep for kitchen work - covered everything up so
that they can paint a little more