Thursday, July 30, 2009

Thursday progress

Guess one of our inspections didn't go well today,
there was piping issues with one of the planters.
Will be working on that issue and
then calling for reinspection of the planter pipes
and then the planters. Still can't install planter plants till all
planters are completely inspected.
The other issue from today is that one of the subs hit a
wire in the Master Bedroom when they
were installing trim. This will be a action
item for tomorrow.
Each day brings some new, exciting issue. Counter tops instlaled in Guest room on built ins


Frosted and non frosted glass installed on roof deck. Other glass
purchased but not yet installed on bridge. Bridge clad work still
needs to be worked on but first floors need to be installed

Rugs on stairs covered but carpeted. Too many people
walking around the house/saw dust
and whatever else makes covering them a necessity.





Everything covered for more painting in Kitchen




Prep for kitchen work - covered everything up so
that they can paint a little more




More Wednesday progress

Light shaft light installed


Carpet on stairs installed today but only
on treads, not risers- that will be bamboo



Cistern installed


Dishwasher installed




Temporary sink installed- our sink is still on
back order for a couple more months






Wednesday progress.....

Installed cabinets under the sink

Cooktop installed under light shaft

Living room cleaned out for rug to be installed today



Upper trim added above tile in Kids bathroom



1/2 Hallway floors installed by Scott and his dad

Wednesday, July 29, 2009

More from Tuesday

Installing counter tops on entire buffet/sink area
as well as cook top section
Prep work for Driveway - getting ready to pour concrete





Added additional rocks close to house on left side to
put a buffer between cars driving
down driveway and the house.
Also widened driveway as well - too narrow before.



Tuesday Mid day

Mad chaos at the house right now to hit Friday's date.
Ran into snafu today with weather being over hundred.
Shouldn't pour cement or do exterior paint when its this hot.
Mother Nature is playing against us with our count down.
Working with team to see how this affects dates/timeline/$
Frames set up for steps to bridge
but have to wait on pouring concrete

ReMDFed wall going to power room
Side counters MDFed, sanded and if
weather permits will be covered today by Asmir.



Tiling on built ins in Nursery
Bamboo floors laid in Nursery- still need quarter round
but it looks great thus far. Color is perfect




Monday, July 27, 2009

Monday Morning

Tar applied to planters and thanks
to Tim/John and Cesar we
now have stoops outside our
dining room doors
Guest Bedroom tile detail on
shelf behind where bed will go

Put hay in the planters on
the roof with Pro Grow soil-
native plants will be planted
tomorrow or Wednesday.



Bamboo floors in Guest Bedroom


Trim is repainted and no longer yellow-
back to basic off white.


Sunday, July 26, 2009

July 25th

Dining Room tiled and needs some more grout

Car is fully loaded after hitting Bosky
Dell Native Plant Nursery. The planters
can only have Native Plants added
to it and specific Pro Gro soil. Hoping
to get planters inspected Tuesday.


Small bathroom with trim, quarter round,
new back splash added and mirror hung


Progress


We are pushing to do our final inspection with city
/bank/appraiser this Friday July 31st.
Its a bit chaotic. :)

Draining Field was dug, piping laid and inspected by city.

The area is a lot more cleared out then we thought it would be.

Master bath now has quarter round,
tile is grouted, mirror added, towel racks hung,
and our most recent snafu - back splash added for sink.
Left is painting is quarter round, trimming,
silicone and some other small details
So we painted trim throughout the house
and turns out the color turned mustard yellow.
Not the effect we were looking for.
So it has to be all repainted. First coat was
added yesterday and second today so
floors can begin.



Rock wall added to far end of driveway,
plants purchased and soil added to planter.


Rest of rocks for driveway
















Sunday, July 12, 2009

July 10, 11, 12

Sink installed in Wood Room-
Frosted glass installed in half bath-
no more peekaboo window :)





More progress

Scott worked on the counter
in the kitchen. This counter is on the right and
left side of the sink. Probably hard to see from the pics.
Thanks to Tim for coming over to help
put in the desk and counter tops
Another view of kitchen- ordered counter tops
and back splash materials. Figuring out sink still- we know
the one we want but its on back order for a LONG time

Back splash- this is where the cook top
will be underneath the light shaft.
Bought a light today for the light shaft.


Trim almost finished being installed in
master bedroom and nursery.



Lights in the hallway----Yahooo





July 10, 11, 12 Progress

Trim around windows and
vanity installed
In progress- Trim in Guest bedroom


In progress- Trim in Reece's bedroom


Medicine Cabinet installed in boys bathroom


Balcony built- really more of a barrier but
glass will be installed next week sometime

Thursday, July 9, 2009

More progress

Some counter tops installed & some just
materials were just ordered.
Upper cabinets doors exist but
haven't been designed/installed yet
Low sitting area added by living room- built by Scott

Triming begun in Dining room by Scott.
Had to forgo having a subcontractor doing this work.
Still have to finish dining room floors-
original tile design scraped due to time though.
Latest design still in Scotts head.