Saturday, January 17, 2009

Exterior Waterproofing/Window pics


Roof deck/light shaft window is installed


Windows/Flashing in Master Suite

2009- Recap

Finished items:
  • Furnace installation/HVAC components
  • Window/Door installation (all but 2- one broken and one missing)
  • Roof
  • Plumbing for now (fixture installation later)
  • Permits (too many to list and more to go)
In progress:
  • Electrical
Soon:
  • Siding

All in windows but one have been installed


Upstairs guest area which walks out to roof deck

Dining Room entrances


Hallway window detail


Saturday, December 6, 2008

The Roof Deck


The railings were framed out this week.
The large openings will be filled
with stainless steel cable
and the smaller openings
with light boxes.


Railing at the entry


The roof deck
with guest apartment beyond

Reece likes to help with the sawdust

The exterior doors have arrived!

Framing continues...

The entry is on the top floor.
We inset the door and adjacent walls here
to break up 'the box'

The hallway
separates the bedroom areas.
Being on the south
side of the house,
we will get lots of light here.

A view of the SW corner

The daylight/ventilation shaft
from the kitchen
20 feet below.

Framing a view


Stairs to the Master